Trilogy of Transformers for Collett Heavy Haulage

The first of three transformers leaves Stafford safely secured in our girder bridge.

Trilogy of Transformers for Collett
Having never utilised our girder bridge to transport transformers from this Stafford manufacturing facility in the past, we mobilised to the West Midlands. Arriving in modular form at the site, our Team constructed the girder bridge before loading the 216 Tonne cargo.
Departing site on Sunday our Team travelled the 35 miles to overnight at Davenport. Under Police and private escort throughout, the following day our convoy completed the journey to Ellesmere Port, concluding the 70 mile journey and offloading the transformer to the port storage area.
Our Team have already returned to Stafford to undertake the second movement, with the third scheduled for mid-November.

1 comment:

  1. I’ve been surfing online more than three hours today, yet I never found any interesting article like yours. It’s pretty worth enough for me. In my opinion, if all webmasters and bloggers made good content as you did, the web will be a lot more useful than ever before. Europa-Road túlméretes szállítás